Spruce Pine details FEMA claims and recovery grants as repair work moves forward
Summary
Town staff described a $7.4 million preliminary damage inventory, pursuit of an expedited FEMA project that could pay roughly half the estimated costs up front, and multiple grants funding waterline and stormwater projects, while DOT returned pedestrian-bridge funds.
Get email alerts on the Disaster Recovery topic
No spam. Unsubscribe anytime.
Town staff told the Spruce Pine council on Dec. 9 that the municipality has compiled a preliminary damage inventory totaling roughly $7.4 million and is pursuing an expedited FEMA project intended to provide partial up-front reimbursement to support immediate repairs.
Finance staff described efforts to package estimates to qualify for expedited payment, saying the approach could yield about "3 and a half million" dollars up front while remaining costs would require full documentation and justification. Staff noted the town has been spending from general and utility funds while FEMA and insurance processes continue and is creating a separate FEMA project fund to keep recovery receipts and payments separate.
Staff also reviewed awarded and pending grants for infrastructure recovery: a Golden LEAF grant of $775,349 and an EDA Department of Commerce grant of $1,000,484 together fund the Highway 226 waterline replacement (totaling roughly $1,484,275), NCDEQ grant awards for water and wastewater asset inventories (about $150,000 each) and a $300,000 stormwater asset-inventory grant. Withers Ravenel is listed as the engineering firm on several of these projects and High Country Council of Governments is assisting with administration.
On the pedestrian bridge, staff said the DOT terminated the construction agreement and will return funds the town had paid; staff added the town has included the bridge in FEMA damages and will discuss next steps with DOT and FEMA.
Staff described other recovery costs included in FEMA estimates: a large contractor line item, portable sewer-plant lease costs and equipment replacement. Staff said they have opened a dedicated bank account to hold any expedited FEMA receipts and plan to return interest earned to recovery costs consistent with guidance.
Officials warned that additional documentation — inventories, justifications and grant reporting — will be required before receiving full FEMA reimbursements. Council members asked staff to continue working with FEMA, the state and grant administrators to secure available funding and to present a FEMA project ordinance at a future meeting.