Summary
Board members heard that water and sewer fund balances improved year over year, approved a $365.49 goodwill billing adjustment, and received an engineering update on near-complete ARPA spending, Mill Street bridge inspection, PCBs in bank-stabilization soils and a planned leak-detection survey.
Get email alerts on the Wpca Finance Engineering topic
No spam. Unsubscribe anytime.
At the regular session following the special meeting, Middletown’s Water Pollution Control Authority reviewed financials, approved a billing credit and received a broad engineering update on ongoing infrastructure work.
Staff reported the water fund cash balance at $2,015,005.21 as of Nov. 8, 2024 — a year-over-year increase of $635,000.67 — and the sewer fund balance at $2,440,465 (an increase of $1,068,533). The chief engineer credited the transition to quarterly billing for improved cash flow.
The board approved two transfers reported by staff: $25,000 moved from sewer depreciation (vehicle replacement) to pump-station repair (to buy spare pumps and support Newfield Street work) and a $10,000 intra-year transfer to pump station repair lines. The transfers were reported as compliant with purchasing and finance regulations.
The board also approved a goodwill adjustment for a customer at 835 Long Hill Road after staff found an apparent consumption spike (6,000 cubic feet). Staff recommended a credit of $365.49 ($116.87 water; $248.62 sewer) based on averaging prior bills; board members noted interest charges are not waived per statute.
In engineering reports, Chief Engineer Brian Robillard said the department has spent about 98% of its originally allocated ARPA funds and expects roughly $120,000 may remain pending final council accounting. Projects highlighted included a contract with AI Engineering for an inspection of the aging Mill Street utility bridge, nearly complete rehabilitation work on projects numbered 25/26 and a new award to In Situ Form Technologies for project 27. A Basin 12 flow study was scheduled to resume after recent rain events to collect data on inflow/infiltration in the north end of town.
Staff also disclosed detection of PCBs in soils generated from a bank-stabilization effort at a previously industrial parcel; those soils are being stored on-site under cover while the department consults engineers and legal counsel about disposal options. Separately, the town plans a satellite/airborne leak-detection survey funded by ARPA that will generate leads for two weeks of field crew follow-up to locate and repair leaks.
The board adjourned after announcing a departmental holiday gathering and scheduling follow-ups for project design and funding.