At a July 13 meeting, the Transportation and Environment Committee deferred two water-and-sewer category change requests (Potomac and Clarksburg), approved sewer service for a rebuilding Seventh‑day Adventist Church in Spencerville, and denied a Muncaster Mill Road request tied to unpermitted apartment units. Staff will draft resolution language for a July 28 council vote and the items will be revisited as part of a 10‑year water and sewer plan update.
Get email alerts on the Water And Sewer Plan topic
No spam. Unsubscribe anytime.
The Transportation and Environment Committee of the Montgomery County Council on July 13 deferred two sewer‑service category‑change requests, approved a sewer hookup for a Spencerville church rebuilding, and denied a request tied to unpermitted apartments at Muncaster Mill Road.
Committee staff presented four separate category‑change requests. Mr. Levchenko summarized the items and said the executive and planning staff recommended denial in two cases but approval in one; the committee voted to defer consideration of two items to give staff time to include them in the county's upcoming 10‑year water and sewer plan work and to allow additional technical review.
Why it matters: Decisions on category changes shape where public sewer can be extended in Montgomery County and can trigger reexamination of local policies (for example, the Potomac peripheral sewer policy and the private institutional facility or PIF policy). The committee flagged system capacity, precedent‑setting concerns and pending Maryland Department of the Environment (MDE) review as key constraints.
Details of the four requests
Piney Meeting House Road (Potomac): Staff recommended denial, committee deferred. Levchenko described a 1.5‑acre RE2 vacant lot in the Trevilla area seeking service for a single‑family home and noted the parcel sits inside the Piney Branch Special Protection Area and outside the planned sewer envelope; none of the water‑and‑sewer plan exceptions (failed septic, abutting main, special sewer service area or Potomac peripheral policy applicability) applied. Tim Williamson of DEP said a WSSC study found "they have capacity in the Palatine low pressure system," but that serving the neighboring failed‑septic property would require a 1,700‑foot extension because of site slopes and low‑pressure system constraints. Alan Soukup (DEP, Watershed Restoration) said the applicant has indicated interest in a three‑lot subdivision that would require the extension and a possible change to the Potomac peripheral policy. Committee members agreed to defer action so staff can craft draft resolution language that notes the deferral reasons and outlines conditions for reconsideration (including WSSC approval and action by the neighboring property owner).
Clarksburg Road (Clarksburg): Staff recommended denial, committee deferred. Levchenko described a 5.7‑acre RE1 site north of Old Baltimore Road proposed for an assisted‑living facility now estimated at about 40 beds. He said the executive recommended denial because no plan exception (failed septic, abutting main, or nonprofit institutional policy) clearly applied; the planning board supported approval citing senior‑housing needs and urged a broader policy review in the 10‑year update. Committee members expressed concern about precedent and noted that MDE previously declined to approve a broadly framed commercial‑service policy; they opted to defer the matter for consideration in the 10‑year plan so any new policy would be developed with additional analysis.
Spencerville (New Hampshire Avenue) — Seventh‑day Adventist Church: Approved. The committee supported an application from the church to rebuild after a 2024 fire. Levchenko said the 8.9‑acre site abuts a gravity sewer main and planning staff determined providing sewer was consistent with the Cloverly master plan and nonprofit‑facility policy, so executive, planning board and council staff recommended approval; the Chair said the item was "an easy one" and supported it.
Upper Rock Creek (Muncaster Mill Road): Denied. The committee denied a request from a 2‑acre RE2 property where the owner has an existing home and separate, unpermitted apartment units. Staff said the additional units were not permitted and there was no plan exception that would allow service; the legal and permitting status of those units is being resolved in court and cannot form the basis for approval.
Quotes and notable lines
Tim Williamson (DEP Water and Sewer): "They have capacity in the Palatine low pressure system." (on WSSC study results and Palatine system capacity)
Alan Soukup (DEP, Watershed Restoration): "We have a strong indication from the applicant that they want to pursue the 3 lot subdivision on this site, which would require also that 1,700 foot long extension." (on the Potomac/Piney Meeting House lot)
Councilwoman Balvin: "It just doesn't make sense to me." (on why a small island parcel surrounded by sewer was left out of the envelope and why senior housing was being denied while surrounding development proceeds)
Next steps and timeline: Staff will prepare draft resolution language reflecting the committee's deferrals, approval and denial for the full council to act on July 28. Committee members also signaled they expect a substantive conversation in the fall when the county takes up the comprehensive 10‑year water and sewer plan update.