Odessa staff recommend using reserves to complete $3.94 million sidewalk project
Summary
City staff presented a final sidewalk bid and proposed funding plan totaling about $3.94 million that would increase the general-fund transfer and draw on transportation and electric reserves while limiting the CIP transfer to preserve capital reserves.
Get email alerts on the Infrastructure Sidewalks topic
No spam. Unsubscribe anytime.
City of Odessa staff told council members the long-running sidewalk project now has final bid numbers and proposed a funding package that would total about $3.94 million, funded by grant income, expanded transfers from the general fund, transportation reserves and an electric-fund contribution.
Staff said the project’s final construction and engineering bids produced a concrete total and recommended increasing the general-fund contribution from $600,000 to $1,000,175 while using transportation reserves (approximately $838,000 available) and an electric-fund transfer. Staff proposed reducing the previously planned CIP transfer from $500,000 to $350,000 so the CIP fund would remain at a roughly 26% reserve level after the transfer.
Why it matters: staff characterized the sidewalk project as a five-year undertaking that has reached a final cost and argued that using reserves is appropriate to finish a multi-year infrastructure effort rather than continuing to delay work. Staff noted some utility funds would still maintain healthy reserves after the transfers.
Council reaction included caution about depleting reserves but several participants voiced support for proceeding. As one staff speaker put it, completing the decade-long project now ‘‘is the opportunity to use the funds to get the project done and be done with it.’’ Others repeatedly asked whether the city should wait; staff said waiting carries ongoing liability and the project has already been put out to bid twice.
What’s next: staff will refine the transfer amounts in the CIP workshop materials and will include the sidewalk funding plan in the final budget package for formal consideration. No final vote or formal approval of transfers occurred at the workshop; the items remain recommendations to be adopted through the regular budget process.
Ending note: if approved in the budget, the transfers outlined would lower general-fund reserves toward the city policy target but would allow the sidewalk project to proceed with construction-level funding.