Belgrade says HEC remodel on tight budget after asbestos abatement doubles estimate

Belgrade City Council (workshop) · July 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told council an asbestos abatement estimate for the HEC remodel rose to about $300,000 (from roughly $110,000), pushing the project budget to $1.85 million; staff expects a guaranteed maximum price in the next two weeks and is monitoring potential funding options including newly taxable values or general fund balance.

City staff briefed the council on the police-and-courts (HEC) remodel and related City Hall moves, saying asbestos abatement and other add-ons have tightened the project budget and that a guaranteed maximum price (GMP) is due within weeks.

Staff said asbestos abatement came back “just under just under $300,000” — far above an earlier estimate of roughly $110,000 — and that the HEC remodel total now sits at about $1.85 million after a recent $250,000 transfer to the project. The general-contractor team (Hasselton, Haddonbury, Eddy, with Hasselton leading) has completed construction documents and moved to the bid phase, and staff said they “should receive a GMP... within the next 2 weeks.”

Staff flagged specific budget concerns that may not fit the base scope, including access control for the building and HVAC work to provide non-window-unit air conditioning in courtroom areas. They described how small unanticipated add-ons can accumulate: “10,000 here, 10,000 there… next thing you know… you're at a $100,000 of add ons.”

On funding options, staff said one possibility is diverting newly taxable value to the project when certified values are received, or using unrestricted fund balance as a less-preferred alternative. Staff also reiterated a prior promise not to ask voters for a bond to support the project for at least five years.

Staff reported one cost-saving for related infrastructure: a planned project to bury fiber was originally budgeted at about $160,000 (split 50/50 with the school district) but changes in the termination point and use of existing private fiber reduced the bill to roughly $90,000.

Next steps: staff will review the GMP when it arrives, continue to track add-ons, and return to council with tighter numbers and funding recommendations.