Kinston awards $295,805 belt filter press refurbishment to Andritz with 10% contingency

Kinston City Council · January 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city awarded a contract to Andritz to refurbish a failing belt filter press at the wastewater treatment plant for $295,805 plus a 10% contingency; council approved the award unanimously and staff said any additional $25,385.50 would come from the wastewater capital reserve.

The Kinston City Council voted unanimously on Jan. 20 to award a refurbishment contract for a belt filter press at the city's wastewater treatment plant to Andritz for $295,805, with a 10% contingency that brings the total award to $325,385.50.

Public Services Director Steve Miller told the council the belt filter press, installed in 2007, squeezes biosolids to remove water and thereby reduces disposal costs; it has begun to fail. Bids received Dec. 19 included options to replace or refurbish rollers. Miller said the refurbishment option was substantially less costly than full replacement ($381,356) and would provide an expected service life of 15–20 years compared with 20–25 years for a full replacement. He explained the 10% contingency would cover any rollers that required replacement after inspection and that if the contingency were used staff would return with a budget amendment to take $25,385.50 from the wastewater capital reserve rather than the general fund or wastewater fund balance.

Council Member Lipford asked whether the additional $25,385.50 beyond the budgeted $300,000 would be the only extra cost; Miller confirmed it would. The award was approved by unanimous vote.