Beaverdam board gets Shaw Hill Bridge update; ditches, roads and code revision work discussed
Summary
The town attorney told the board that Union Pacific is still reviewing a transfer agreement for Shaw Hill Bridge and noted an October grant deadline; the board also heard road and ditch work updates, planned bids for a gravel road, and that a Chapter 10 code revision draft is complete.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town officials on Aug. 12 received an update on several infrastructure and code items, including progress on the Shaw Hill Bridge transfer and local road and ditch work.
The town attorney reported Union Pacific's legal department is still reviewing a proposed transfer agreement for the Shaw Hill Bridge; the attorney said a grant submission to support work on the bridge is due in October. No transfer agreement was finalized at the meeting.
Road and maintenance reports included that Zimmerman Drive ditch work by contractor R.C. Koch is complete and that town maintenance crews will apply grass seed and straw. Kartechner Bros. will provide a preliminary bid for gravel work related to Schoenfeld's Woodland Plat, and Joe Kern said he is working to obtain a surveyor to prepare a legal description for property on McKinley Beach Road. A resident request for permanent speed bumps on McKinley Beach Road and National Drive was noted in correspondence; the board did not act on that request at this meeting.
The Road Maintenance Department reported a quote from Garage Door Specialists for new Town Hall garage doors; the board will obtain additional quotes before making a decision. Board member Dave Raue had gathered information about a replacement mower but was not present to discuss it; the board will follow up when quotes and details are available.
The town attorney said a draft revision to Chapter 10 of the town code is complete and will be reviewed by peers prior to further board consideration. The attorney was identified in the minutes only by title; no personal name was recorded.
Why it matters: The Union Pacific review and the October grant deadline create a time-sensitive window for bridge funding and transfer steps. Road and drainage maintenance items affect local travel and property access, and the Chapter 10 draft could change local code enforcement and permitting once the board reviews it.
Next steps: The town will continue to collect contractor quotes, pursue the surveyor for McKinley Beach Road, and return with draft Chapter 10 revisions and procurement details at future meetings.