Beaufort airport board accepts state grants for radio upgrades and Runway 725 rehab, approves related work authorizations

Airport Board · September 19, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The airport board approved two South Carolina Aeronautics Commission grants—$140,004 for tower radios and $157,006 for Runway 725 rehabilitation at ARW—authorized construction administration and drainage design work, and voted to renew a USDA wildlife contract (approx. $15,000).

The Beaufort County airport board voted to accept two South Carolina Aeronautics Commission grants and approved several related work authorizations during its meeting.

John, the airport director, told the board the first grant is for $140,004 to replace four radio sets in the air traffic control tower so all equipment is modern and interoperable. "So all the radio equipment will be up to snuff, modern, new technology," John said, explaining the replacement addresses compatibility issues between older and newer sets. The board moved and approved the grant acceptance by voice.

The board also approved a second SC Aeronautics Commission grant of $157,006, described by John as the 5% local share for the Runway 725 rehabilitation project at ARW. John said bids are in and a responsive low bidder has been selected; the construction contract will be presented to the board at a future meeting. The board moved and approved acceptance of the grant.

Members authorized construction administration and inspection services from Talbot Bright & Ellington for the Runway 725 project; John confirmed this work will be funded by the grant package. The board approved a separate work authorization for design and bidding services to upgrade airfield drainage structures at Hilton Head Island Airport to meet C3 strength requirements.

On wildlife control, John said the airport has re-engaged the U.S. Department of Agriculture for on-call services after a previous contract ended. He identified the contract amount as about $15,000 and the board approved a resolution to restore USDA support for wildlife removal and mitigation at both airports.

No recorded roll-call tallies were included in the meeting discussion; approvals were taken by voice after motions and seconds were solicited. The board indicated it will bring final construction contracts and additional project details (including schedule and notice-to-proceed dates) to upcoming meetings.

The board adjourned after completing the listed agenda items.