Contractors tell Beaufort County meeting that aggregate and sand allotments limit local paving capacity
Summary
A contractor representative said statewide sand/aggregate allotments and shipping constraints limit how much asphalt local producers can make, complicating the county’s ability to spend large state funds quickly.
Get email alerts on the Contractor Supply topic
No spam. Unsubscribe anytime.
A contractor representative told the Beaufort County Transportation Committee on Sept. 18 that material and production constraints — not just the number of local firms — limit how quickly resurfacing work can be performed.
The speaker (S7), a local area manager for an asphalt producer, explained that sand and aggregate allotments and quarry output create hard production limits. "We are on a sand allotment of a 100 tons a day ... I can only produce 2,500 tons of asphalt if I want to with sand in it," he said, adding that only a portion of quarried rock can be processed into the specific "number 7 stone" required for certain mixes and that that stone is shipped across counties. He said that major, out-of-area projects can pull crews and material away from local jobs.
Committee members and staff acknowledged the constraints. Staff warned that even with newly available state funds, executing a high volume of projects within a single spending window will be difficult unless material and production bottlenecks ease.
The committee agreed to explore options for vendor coordination and to invite contractors to a proposed February retreat to discuss products, production capacity and local sequencing.
What was said (excerpt): "There is a gross allotment of tons that are allowed to be made in the state ... only 10% of that rock can create a rock called number 7 stone ... if I had a crew in Charlotte or Greensburg, I won't put a 95 tomorrow, I couldn't." — S7 (contractor representative).