Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

County'commissioner-appointed review finds Justice Center close to original financing estimate; dewatering and change orders account for most differences

Boone County Council · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A financial review of the Justice Center accounting and contracts found the guaranteed maximum price paid to the contractor totaled about $59.15 million, change orders added about $1.5 million, and FF&E costs paid from local income tax were about $5.86 million; after reconciling bond payments and other items the reviewer concluded the project was not $7 million over budget as previously suggested.

County staff presented a review of the Justice Center financials after questions that the project might be roughly $7 million over anticipated costs. The presenter said she and staff reviewed a banker's-box collection of documents, contractor invoices, bond-fund transactions and change orders to reconcile totals.

Key figures presented: the guaranteed maximum price (GMP) contract with GM Development was $59,151,323; change orders totaled roughly $1.5 million (with drainage and dispatch rework among the larger items); and furniture, fixtures and equipment (FF&E) paid from local income tax totaled about $5,856,685.11. The reviewer said that some payments recorded in the bond fund appeared to be bond payments or transfers to treasurer/commissioner line items and therefore not direct construction fees.

After backing out bond payments, FF&E paid outside the bond proceeds, and approved change orders, the presenter concluded the total project costs the team could attribute were close to the anticipated funding envelope and not near a $7 million overage. The reviewer identified dewatering as a primary cause of an unanticipated increase (the dewatering allowance was originally $50,000 but final costs recorded near $176,009), and said more granular follow-up could examine whether specific drainage/floor-drain items were missing from original drawings or arose during construction.

Council members asked for additional detail on specific items (architectural drawings, the origin of change orders and fund accounting); the presenter said staff could dig further into the drainage question and supply clarified documentation.