Avion Ventures warehouse reduced in size after DEC wetland finding; Board to seek wetland validation and traffic study
Summary
The Board declared intent to act as lead agency for the Avion Ventures warehouse project and authorized recirculation of adjoiner notices after DEC confirmed the site is within NB‑21 freshwater wetland adjacency; the applicant reduced building area, added emergency access, and was instructed to provide wetland validation, traffic analysis and City sewer‑flow acceptance.
Get email alerts on the Avion Ventures Warehouse topic
No spam. Unsubscribe anytime.
Justin Dates of Colliers presented a revised speculative warehouse proposal on Pomarico Drive reduced to 56,000 square feet from 62,500, with emergency access all around the building and six loading docks. "The DEC does confirm it is part of the NB-21 New York State DEC freshwater wetland," Dates told the Board, noting he will pursue a DEC validation map and necessary adjacent‑area permits.
Pat Hines said the applicant must provide a wetland validation survey and work with DEC on any stormwater improvements that encroach into the adjacent area; Hines also flagged the EAF note about potential bat habitat and said tree‑clearing restrictions could apply. The Board also directed the applicant to provide water and sewer plans and a City of Newburgh flow‑acceptance letter.
The applicant and Board discussed private‑road access on Pomarico Drive; Dates said the title opinion provided shows deeded access and that Colliers will submit a survey and plans for road improvements and utilities down Pomarico. "We will be conducting a full survey of the right‑of‑way limits, all the existing improvements," Dates said, and confirmed sewer and water connections will be extended to serve the site.
The Board voted to recirculate adjoiner notices and to declare intent to be lead agency, enabling SEQRA circulation (including DEC and DOT) and consultant review of the traffic study once submitted. Consultants emphasized that DEC wetland validation is a gating issue and that the City sewer‑flow letter will be required before final approvals.
What the applicant must provide - DEC wetland validation/permit for NB‑21 adjacent‑area work. - Traffic study to be circulated to Creighton Manning and Town consultants. - Water/sewer design and a City of Newburgh sewer‑flow acceptance letter. - Clarification of private‑road rights and a plan for Pomarico Drive improvements.
Next steps The Board will circulate the notice of intent for lead agency and the applicant will provide the wetland validation and traffic study to Town consultants for review. Final site‑plan approval will be conditional on DEC, DOT and City approvals.