Scobey K-12 board accepts $112,843 roof bid, approves handbooks, routes and personnel hires

Scobey K-12 Schools · July 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Scobey K-12 Schools board accepted a $112,843 bid from Dale Brothers for a 90-mil roof on the elementary and music buildings, approved related membrane-prep work (about $23,000), and signed off on handbooks, attendance agreements, bus routes and several hires for 2025–26.

The Scobey K-12 Schools board voted to accept a $112,843 bid from Dale Brothers to replace the elementary- and music-building roofs and approved related membrane-prep work and several routine items for the 2025–26 school year.

The motion to accept the Dale Brothers option 2 bid for a 90‑mil system was made by a committee member (S7) and seconded; the board approved the contract by voice vote. During discussion, a presenter (S6) emphasized that bid specifications must include Montana prevailing-wage requirements and proof of insurance and bonding. “Montana also requires prevailing wages for any public works,” S6 said, warning that omitting the language can expose the district to claims by workers.

The board also approved an approximate $23,000 membrane-prep cost for the elementary roof section so the contractor can install two layers as specified. The presenter described warranties and life-expectancy differences among membrane options, noting that thicker membranes carry longer material warranties and hail coverage.

In the same meeting the board approved several routine administrative items: recommended handbook changes for the 2025–26 school year, attendance agreements for several out-of-district students, and bus routes for 2025–26. The board approved hiring Skip Baldy and Peyton Lybrand as bus drivers pending background checks and endorsement completion, and approved paraprofessionals Kylie Anderson and Ariana Anderberg, also pending background checks. Assistant coaching assignments for the high school and junior high were approved as presented.

Votes at a glance • Dale Brothers bid (option 2, 90‑mil) for elementary and music roof — motion carried (moved by Committee member S7). Contract amount: $112,843. • Membrane-prep for elementary roof — motion carried. Presenter referenced a prep line item of roughly $23,000. • Handbook changes (2025–26) — motion carried. • Attendance agreements (2025–26) — motion carried. • Bus routes (2025–26) — motion carried. • Bus driver hires (Skip Baldy, Peyton Lybrand) — motion carried (pending background/endorsements). • Paraprofessionals (Kylie Anderson, Ariana Anderberg) — motion carried (pending background checks). • Assistant coaches list — motion carried.

Board members said contractors will coordinate insulated-area inspections and telephone-line work to limit disruption before school starts. The board set the next budget meeting for July 19 to allow staff time to collect final budget figures.