Board of Public Service presents $36.6 million low bid for Lambert runway reconstruction
Summary
On July 14, 2026, the St. Louis Board of Public Service was presented with a recommendation that Millstone Webber LLC’s $36,639,024.35 low bid receive preliminary approval for reconstruction of Runway 12L–30R at Saint Louis Lambert International Airport (letting 8794). No final action on the contract was recorded at the meeting.
Get email alerts on the Airport Infrastructure topic
No spam. Unsubscribe anytime.
On July 14, 2026, the St. Louis Board of Public Service heard a president’s recommendation that preliminary approval be given for letting number 8794, the reconstruction of Runway 12L through 30R from Taxiway S to Taxiway L at Saint Louis Lambert International Airport.
“The lowest responsible bid was received from Millstone Webber LLC in the amount of $36,639,024.35,” the board’s secretary read during the agenda presentation. The recommendation was presented as a preliminary award; the meeting record does not show a final vote on the contract during the session.
The agenda packet also named a proposed contractor for letting number 8795 (Compton Avenue over Union Pacific Railroad replacement, federal project STP-5451) and noted the contractor had furnished a required performance bond under the city charter. The secretary read a temporary license agreement for early construction activities with the Boys and Girls Club of Greater Saint Louis that would allow limited entry to the license area while a street/alley vacation is processed.
None of the construction-contract recommendations listed during the agenda portion of the meeting were recorded as final actions at the July 14 meeting; the board moved on to approve meeting minutes and other procedural items after the agenda items were read.