Town examines water and wastewater projects as AMI meters, plate-settlers and sludge options surface
Summary
Town staff outlined water-system upgrades including AMI meters (staff conservatively projected a 15% revenue increase), a proposed plate-settler project estimated at $645,000 with possible state funding, and ongoing sludge-disposal challenges after a high-cost outside quote was declined.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Staff member (S2) reviewed several active and proposed water and wastewater projects, and the board discussed funding options, projected revenue changes from new meters, and alternatives for sludge disposal.
On metering, S2 said presentations at the state level show "most AMI projects see a 35 percent increase in revenue," but she took a conservative approach and modeled a 15% revenue increase for the town in the budget. She also reported the water system has just under 1,100 customer connections.
S2 described a proposed plate-settler capital project to improve basin processing and winter operations, with a projected cost of $645,000. She told the board there is roughly $1.2 million in state direct funding available that could be applied; engineering and coordination with the AIA mapping process were requested before proceeding.
On sludge, S2 said the town received a quote from Waste Management to remove sludge using a centrifuge and haul it to a landfill for about $300,000, and the board declined that option. She said land application remains the current practice and staff will continue to look for cost-effective alternatives.
S2 also outlined smaller but operationally important items: filter-rehab work quoted around $53,000, chemical-feed-pump spares at approximately $3,500 each, and a planned SCADA second-phase rollout to consolidate monitoring and control systems.