Council approves $688,097 amendment for Macau Road widening design
Summary
Council approved an amendment to a professional services agreement with LAN for Macau Road widening (Broadway to Beltway 8) that adds TxDOT-2024 standard updates, Atlas 14 drainage design, and acquisition services; staff expects 95% design in five months and right‑of‑way acquisition within about a year.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
City staff presented an amendment to the professional services agreement with LAN to update design plans for the Macau Road widening project between Broadway and Beltway 8. The amendment includes updating plans to TxDOT 2024 standards, revising drainage to meet Atlas 14 criteria, adding right‑of‑way acquisition services, and including project elements required for coordination with the Clear Creek Drainage Project. Staff recommended approving an amended contract amount of $688,097.
Staff outlined a project schedule: 95% design within five months, right‑of‑way acquisition by about this time next year, utility relocations to follow, and TxDOT advertisement targeted for September 2028 with approximately 2½–3 years of construction once awarded. Council had no substantive questions and approved the amendment by a 7–0 vote.