Town reports progress on Preston Road waterline and pump station; crews nearing connection work

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials reported installation progress on a one-mile waterline on Preston Road, pickup and installation of 12 lengths of 12-inch pipe, scheduled bridge crossing work, and completion of training and punch-list items at the new pump station pending a crane to lift pumps for final hookup.

Town staff provided a brief infrastructure update describing recent progress and remaining work on waterline and pump station projects.

Wayne reported crews installed a blow-off on the new mile of waterline on Preston Road and brought in 12 lengths of 12-inch pipe from Public Works for installation. Pipe was installed to a point near the bridge; crews plan to skip the bridge and make a connection on the far side and are coordinating a scheduled bridge crossing. Wayne said he did not yet have written correspondence with a final bridge schedule but that scheduling conversations are active.

At the pump station, staff completed training on the biocide system and pump systems and await delivery of a crane so pumps can be removed or installed as required; punch-list items include painting exposed steel and resolving a couple of fence issues. Wayne said that once a water connection is made the pump station can be connected and fully commissioned.

Board members expressed encouragement and urged the team to complete outstanding items; staff committed to follow-up work and to updating the board when connections are complete.

Next steps: schedule bridge work, secure crane delivery to handle pump work, and complete punch-list items before final commissioning.