Kellnersville approves water-tower closeout documents, schedules catch-basin repair and hydrant replacement

Village Board of the Village of Kellnersville · February 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Village Board approved pay request #3 and a certificate of substantial completion for the water tower paint project, agreed to proceed with a spring catch-basin replacement (preferring Essential Sewer & Water), and noted the park water-main coupling was tightened with asphalt repairs pending and a pond hydrant replacement scheduled for Feb. 12, 2026.

The Village of Kellnersville on Feb. 9 approved documents closing out work on the water tower paint project, reviewed replacement quotes for a catch basin at the K and T intersection, and received a utility report on a repaired water-main leak and an upcoming hydrant replacement.

Trustee Scott Totten moved and Trustee Jason Kolb seconded approval and signing of pay request #3, the SDWLP disbursement request #4, and the certificate of substantial completion for the water tower paint project; the motion carried unanimously. The minutes record that the board approved those documents as presented.

Utility operator Todd Lensmeyer reported a coupling that previously failed underground at the park was tightened by Essential Water; asphalt repair remains necessary. Lensmeyer also reported the hydrant at the ponds is scheduled to be replaced on Thursday, Feb. 12, 2026.

For a catch-basin replacement at the intersection of CTH K and CTH T, Lensmeyer presented two quotes: Essential Sewer & Water at $13,000 and DeGroot Construction at $11,500. County advisor Greg Grotegut recommended completing the work in spring 2026 rather than waiting for county work in 2027 to avoid collapse; Lensmeyer recommended using Essential Sewer & Water based on prior performance, and the board agreed.

The board later approved utility payables totaling $28,460.05 (including a $13,500 transfer from the money market to checking) as presented.

Next steps: Staff will sign and file the water-tower completion documents, schedule asphalt repairs for the park water-main area, proceed with the selected contractor for the catch-basin replacement this spring, and complete the hydrant replacement on Feb. 12, 2026.