Developers report progress on 30‑unit Herriman Hill affordable housing; cost estimate about $13M
Summary
A developer updated the select board on construction progress for the Herriman Hill project (30 affordable units): framing, insulation, roofing and partial interior work are complete on several buildings, with an estimated total project cost of about $13 million and roughly $5 million remaining to finish construction.
Get email alerts on the Affordable Housing topic
No spam. Unsubscribe anytime.
Officials and project staff updated the Wolfeboro Select Board on May 20 on construction of the Herriman Hill affordable housing project, a 30‑unit development supported in part by Community Development Block Grant (CDBG) funding.
A project representative said exterior framing, foundation insulation and roofing are complete on the buildings, with siding, windows, interior drywall and mechanical rough‑ins in progress on several units. The presenter said sprinklers have been installed and inspected in roughly half the buildings and that remaining tasks include a dumpster pad, propane tank pad, sidewalk tip‑downs, final plumbing/electrical/HVAC work and landscaping. The schedule calls for project completion in July.
Board members asked for additional details such as square footage and unit mix; a project developer estimated per‑square‑foot construction costs "running between $300 to $400 per square foot," consistent with low‑income housing tax credit projects in the region. The presenter estimated total project cost at about $13,000,000 and said approximately $5,000,000 remained to complete the work.