Nash County approves engineering contracts and project budget actions for sewer, water and emergency services projects
Summary
The board awarded multiple engineering contracts (Stocks Engineering and The Wootton Company), approved a Stocks Engineering task order for an emergency services warehouse, and adopted a grant project budget amendment for Middlesex Corporate Center; all actions passed by voice vote.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Nash County Board of Commissioners approved a package of infrastructure actions on July 13, including engineering services awards and a budget amendment tied to phase 2 improvements at the Middlesex Corporate Center.
Staff recommended awarding engineering services for Project Patriot — a 1,200-foot sewer extension to serve Freedom Industries and surrounding parcels — to Stocks Engineering. The package calls for the firm to provide preliminary and final design, construction administration and observation. The board approved the award after staff said Stocks had the strongest technical approach among four proposers and that the county attorney and county manager would review contract documents.
The board also awarded engineering services for a roughly 1,100-foot water main extension to serve two outparcels at the Middlesex Corporate Center and authorized the county manager to execute a contract with The Wootton Company. Commissioners questioned the estimated engineering fee (noting the percentage appeared high on a small project) and staff explained that smaller projects often show higher engineering fees as a percentage of construction cost because of fixed overhead and limited economies of scale.
Separately, the board approved a master services agreement and Task Order 1 with Stocks Engineering (corrected in the packet from $49,300 to $39,300) to perform site civil design for an emergency services warehouse adjacent to Nash Community College and authorized the manager to execute the documents.
Staff also presented an amendment to attach final expenditures to the grant project budget ordinance for Middlesex Corporate Center Phase 2 (sewer, road and electric). The amendment reallocates remaining funds to extend water service to an additional parcel and reflects that grant funds have been expended and reimbursed. The board approved the amendment.
Votes at a glance (all by voice, motion carried): - Award engineering services to Stocks Engineering (Project Patriot): approved. - Award engineering services to The Wootton Company (Middlesex water extension): approved. - Approve Stocks Engineering master services agreement and Task Order 1 (emergency services warehouse): approved. - Approve grant project budget ordinance amendment for Middlesex Phase 2: approved.
Why it matters: These actions move forward planned utility extensions intended to support industrial and commercial sites, improve county infrastructure availability and leverage grant funding. Commissioners noted the importance of price transparency and efficiency on smaller projects.
Next steps: County staff will finalize contracts subject to attorney and manager review and notify commissioners of cost estimates and timelines as final documents are executed.