Town Manager Laura Ratcliffe told the council the Virginia Resources Authority loan for Sewer I & I is set to close in October but requires a second public hearing to approve the higher funding amount; she also outlined a mid-September Lakeview water/sewer report, town-hall lobby flooding tied to a cracked drain pipe, and $4,000 in meter hardware replacements authorized to Director Osborne.
Get email alerts on the Infrastructure Utilities topic
No spam. Unsubscribe anytime.
Town Manager Laura Ratcliffe reported that Virginia Resources Authority funding for the town’s Sewer I & I project has Rural Development parity approved and is scheduled to close in October, but the loan closing will require an additional public hearing to authorize the higher financing amount.
Ratcliffe said the town is submitting final paperwork for the Lead & Copper grant and expects the Lakeview/Grayson Street water and sewer planning report by mid-September. She noted several August expenditures related to utilities and capital maintenance, including a $20,400 payment to Hurt and Proffit for initial Lakeview project invoices and a $19,600 capital payment for the police department roof.
Ratcliffe described repeated flooding in the Town Hall lobby. Staff documented water running from the parking lot into a drain pipe that passes under the building and ties to the roof drains; the manager said the working theory is the pipe has cracks that, when overwhelmed, push water through the lobby floor. She said roof-runoff mitigation has reduced the problem from that source, but parking-lot runoff remains an unresolved risk and that replacing the pipe could be cost prohibitive. Further study was recommended.
On utilities operations, Ratcliffe said Public Works replaced 12 meters during August and identified existing meter-reading hardware as end of life. She authorized Director Osborne to purchase replacement components with an estimated cost of $4,000; six accounts remain on manual reads: Core Fit; Grayson County Pool; Grayson County Rec Fields; Guynn Furniture; the Food City Shopping Center tenant meter; and UTI Integrated Logistics.
Ratcliffe also reported that the BZA approved an AEP Peach Bottom variance; that approval is listed in the manager’s report and the AEP variance is on the Town Council agenda for consideration. She asked the council to note the VRA funding public hearing set for Oct. 1 (a special council meeting) as a required next step before the loan can close.
The manager closed with community items: Town Park planting is scheduled Sept. 27–28 and organizers seek volunteers to plant more than 300 plants, and Safe Halloween is scheduled Oct. 31, 5–7:30 p.m. Ratcliffe will be on vacation Sept. 20–Oct. 4; routine staffing and operational adjustments were noted for that period.