Commissioners rescind Northridge sewer project after bids come in far above estimates
Summary
The Lake County Board of Commissioners voted to rescind a prior determination to proceed with the Northridge sanitary sewer extension in Madison Township after engineering bids arrived at roughly double earlier estimates; commissioners cited assessment status and ARPA spending timelines as complicating factors.
Get email alerts on the Infrastructure Sewer topic
No spam. Unsubscribe anytime.
The Lake County Board of Commissioners voted to rescind a prior determination to proceed with the Northridge sanitary sewer extension project in Madison Township after engineering bids came in substantially above the engineer’s estimate.
At the meeting the chair (identified in the transcript as S1) said the engineer’s estimate had been about $4,000,000 but bids were closer to $8,000,000. The chair described the project as an assessment project and said timing for spending American Rescue Plan Act (ARPA) funds complicated moving forward. "I'm disappointed. I would have liked for us to been able to do that project," the chair said during discussion.
The clerk read the rescission resolution before the discussion. After the chair’s remarks the board approved the rescission by roll call (Commissioner Pletchner yes; Commissioner Beveridge aye). The transcript does not record additional roll-call names or a detailed yes/no tally beyond those votes.
Why it matters: Commissioners cited two practical barriers — sharply higher contractor bids and constraints tied to assessment status and ARPA spending deadlines — that together led to stopping the project rather than authorizing construction at the higher cost. The change means the county will not proceed with the current plan to place sanitary sewer lines along Route 20 in Madison Township as previously contemplated.
What the board said: The chair characterized the difference between the engineer’s estimate and bids as "significantly higher" and noted bidders sometimes do not bid when estimates are below reality. A county staff member (referred to in the meeting) confirmed the bids were higher than the estimate. The chair emphasized the financial and timing difficulties as the principal reasons for rescinding the earlier decision.
Next steps: The transcript does not record a new plan or timeline for revisiting sewer infrastructure in the area. The rescission was approved at the meeting and no motion to replace or re-scope the project was recorded.