Ceresco chooses two-plan approach for street work after reviewing Elm Street costs

Village Board of Trustees of the Village of Ceresco · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After reviewing higher-than-expected Elm Street repair costs, the Board adopted a two-plan approach: Plan A to redo 2nd Street Elm–Pine for $58,000 or Plan B, a smaller set of projects totaling lower amounts, subject to attorney approval and potential amendment of the One & Six Year Street Plan.

Trustees reviewed Elm Street mill-and-overlay work and unexpected costs tied to the co-op parking area before debating further street repairs.

Trustee Burklund described extra patching and base work that increased Elm Street project costs, noting $17,000 in patching and additional rock and overages for the co-op parking area. The Board discussed adding two 1st Street segments and portions of 2nd Street to the One & Six Year Street Plan.

Multiple motions followed. An initial motion to do 2nd Street (Beech–Spruce) for $28,400 was made and later rescinded. After further discussion the Board approved a two-plan approach: Plan A would redo 2nd Street between Elm and Pine for an even $58,000; Plan B would perform Beech–Spruce on 2nd Street for $28,400 and also complete two 1st Street overlays ($14,000 and $18,000). The Plan B option was conditioned on attorney approval and amending the One & Six Year Street Plan if needed. The motion adopting Plan A/Plan B (with attorney sign-off requirements) carried unanimously.

The Board did not finalize funding sources during the meeting and instructed staff to consult the village accountant and attorney as needed before contracting work.