Hazen council approves final payment to DSG for water meter replacement

Hazen City Council · October 22, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a negative change order that reduced the DSG contract from $576,795 to $551,288 and authorized payment #3 for $144,617.60, closing out the water meter replacement contract.

Hazen — The city engineer briefed the council on the DSG water meter replacement project and recommended approval of the final payment. Jared said the original contract price was $576,795 and that a negative change order of $25,507 brought the final contract price to $551,288.

"What I'm asking for approval is final balance and change order number 1 for a negative $25,507. That'll adjust the final contract price for DSG to $551,288," Jared said. He recommended approval of payment number 3 for $144,617.60, which would bring DSG to 100% of the new final contract price.

A motion to approve payment #3 was moved and seconded; the meeting transcript records roll-call voting with multiple ayes recorded.

Next steps: The city will issue payment #3 to DSG and close out the contract after the final payment is processed.