Hazen council approves final payment to DSG for water meter replacement
Summary
Council approved a negative change order that reduced the DSG contract from $576,795 to $551,288 and authorized payment #3 for $144,617.60, closing out the water meter replacement contract.
Get email alerts on the Water Meter Replacement topic
No spam. Unsubscribe anytime.
Hazen — The city engineer briefed the council on the DSG water meter replacement project and recommended approval of the final payment. Jared said the original contract price was $576,795 and that a negative change order of $25,507 brought the final contract price to $551,288.
"What I'm asking for approval is final balance and change order number 1 for a negative $25,507. That'll adjust the final contract price for DSG to $551,288," Jared said. He recommended approval of payment number 3 for $144,617.60, which would bring DSG to 100% of the new final contract price.
A motion to approve payment #3 was moved and seconded; the meeting transcript records roll-call voting with multiple ayes recorded.
Next steps: The city will issue payment #3 to DSG and close out the contract after the final payment is processed.