Charlie Grimm Boardwalk bids to open end of August; construction expected winter/spring with completion in 2025
Summary
Bids for the Charlie Grimm Boardwalk are slated to open at the end of August with an award in September; contractors anticipate winter/spring construction and completion by summer 2025, the engineer told the committee.
Get email alerts on the Charlie Grimm Boardwalk topic
No spam. Unsubscribe anytime.
Village Engineer Nick Bubolz told the committee that bids for the Charlie Grimm Boardwalk will open at the end of August, with an award expected in September.
Bubolz said contractors anticipate the work would proceed in winter and spring with an expected completion in summer 2025. The committee did not record further action beyond the update; a formal bid award will appear in future meeting records if and when it occurs.
The update is informational and sets expectations for the project procurement and construction schedule.