Morrison and Maple street work to start in August; Windsor Crossing Conservancy Path to follow

Village of Windsor Public Works Committee · August 13, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee was told Aug. 13 that the Morrison Street and Maple Street improvements will begin in August with an October completion goal; the contractor plans to finish most work in Morrisonville before starting the Windsor Crossing Conservancy Path.

Village Engineer Nick Bubolz told the Public Works Committee that the 2024 Street and Utility Improvements on Morrison Street and Maple Street are scheduled to begin in August and aim for completion in October.

Bubolz said the contractor intends to complete most of the work in Morrisonville before beginning construction on the Windsor Crossing Conservancy Path. Committee members did not record objections and the schedule was presented as part of ongoing project briefings.

The timeline keeps the project on track for the planned October deadline and sequences the path work after most roadway utility work in Morrisonville is finished.