Council approves $484,566.50 payment to Staab Construction for WWTP improvements
Summary
The Forest City Council approved Staab Construction Pay Request No. 19 for $484,566.50 for work completed on the wastewater treatment plant improvements project on June 15, 2026. The motion passed unanimously.
Get email alerts on the Wastewater Treatment topic
No spam. Unsubscribe anytime.
The Forest City Council approved payment to Staab Construction for work completed on the wastewater treatment plant improvements project. Councilmember Brad Buffington moved to approve Staab Construction Pay Request No. 19 for $484,566.50; Councilmember Carly Carper seconded the motion and it carried on a unanimous voice vote.
The minutes record the dollar amount and the pay request number but do not include a payment schedule, retainage, or remaining contract balance. The minutes do not record questions or objections from council members on this item.