Forest City council rejects sole boiler bid of $963,293 and ends replacement project
Summary
After a public hearing on a single bid from Steege for $963,293, the Forest City Council voted unanimously to reject the bid and end the power‑plant boiler replacement project on June 15, 2026.
Get email alerts on the Power Plant Boiler Replacement topic
No spam. Unsubscribe anytime.
The Forest City Council opened a public hearing on June 15 to consider bids for a power‑plant boiler replacement. The record shows the city received a single bid from Steege in the amount of $963,293. After review, Councilmember Dan Davis moved to reject the bid and to end the boiler replacement project; Councilmember Marcia Tweeten seconded the motion, and the council approved it on a unanimous voice vote.
The meeting minutes do not state the council’s rationale beyond the motion to reject the bid, nor do they record alternative procurement steps or a revised timeline. The minutes note that the public hearing opened at 7:02 PM and closed at 7:05 PM; no public testimony is recorded in the minutes. The city did not record a subsequent plan for reissuing the project or funding changes in the meeting text.