Drainage Board approves $27,226 net deduction for Mary Wilson contract, reviews $1.25M McCarty bid
Summary
Hamilton County’s Drainage Board approved Change Order No. 6 for the Mary Wilson Oak Park Drain (net deduction $27,226.74; final contract $654,037.83), accepted a surety recommendation for Ogden Estates, and opened a Morphy Construction bid of roughly $1,252,000 for J.S. McCarty Phase 2, which the board referred to the Surveyor’s Office for review.
Get email alerts on the Construction Projects topic
No spam. Unsubscribe anytime.
The Hamilton County Drainage Board unanimously approved Change Order No. 6 for the Mary Wilson Oak Park Drain during its July 13 meeting, accepting contract line changes that produced a net deduction of $27,226.74 and a new final contract amount of $654,037.83.
Surveyor’s Office staff said the change order included two primary additions — addressing two areas holding water within the easement and restoring power at the Haybig Field concession stand — totaling $16,098.84, and multiple deletions totaling $43,325.58, resulting in the net deduction. Staff recommended approval and the board voted in favor.
The board also heard a bid opening for the J.S. McCarty Drain Phase 2 reconstruction. A bid packet from Morphy Construction included required documents (Form 96, non‑collusion affidavit, insurance certificate) and listed the total bid at approximately $1,252,000.01. The board referred the bid packet to the Surveyor’s Office for technical review and recommended the office report back in two weeks; no contract award was made at the meeting.
Separately, the Surveyor’s Office recommended acceptance of the surety for the James Lockwood drain relocation in the Ogden Estates development; the board acknowledged that recommendation and noted no reported violations.
Staff provided construction updates on multiple projects: Mary Wilson and several other drains were substantially complete; Emily Vestal reconstruction crews were mobilized and moving upstream; contractors remain busy and coordination with Duke Energy on pole relocations is ongoing. Staff agreed to follow up on a homeowners association question about assessments and confirmed no additional payment requests had been submitted to date.
The board scheduled its next meeting for July 27, 2026, and adjourned.