City staff explain 50/50 utility extension deal for Harmony at Arlington development
Summary
City staff described a proposed utility extension agreement requiring a developer to extend a water main beneath Portage Creek to serve two parcels; the city and developer will split directional-drilling costs to bring a 12-inch water main across the creek.
Get email alerts on the Utility Extension Agreement topic
No spam. Unsubscribe anytime.
City staff described a utility extension agreement proposed between Arlington City and Harmony at Arlington LLC under which the developer would extend water utilities across two parcels, including a narrow strip that contains Portage Creek, and donate that strip to the city.
Jim Kelly, the staff presenter, told the council the developer's initial plans showed a water main only across one parcel rather than to the far edge of both parcels. To meet city requirements to extend utilities to the full extent of properties, the project requires horizontal directional drilling to place a water main beneath Portage Creek. Kelly said the city and the developer agreed to split the cost of that drilling roughly 50/50.
Kelly said the project also includes upsizing a 6-inch water main along SR 9 from 204th to 12 inches to meet system needs, and that the city has not had prior problems with the existing under-creek line. Council members asked whether alternative connections were feasible; staff answered they were not and reiterated the need to cross the creek to reach the adjacent parcel. The transcript records discussion and clarification but does not show a formal vote on the agreement during the workshop.
Staff asked council to review the agreement language and cost-sharing arrangement as part of the next formal agenda steps.