Haskell County Commissioners approve contractor-led LED upgrades for two county barns at no cost
Summary
The Haskell County Commissioners approved a contractor-provided LED lighting retrofit for Barns 1 and 2 after a presentation from a representative of Integrity (contractor for PSO). The vendor waived $6,469.19 in equipment and lift costs; county staff said no county funds are required.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Haskell County Commissioners voted to approve LED lighting upgrades for Barns 1 and 2 after a presentation from Shana, a representative of Integrity, the contractor working with PSO.
Shana said the contractor inspected all three barns and that Barn 3 already met LED standards. She told commissioners, “The cost of the equipment that's being, waived for us is $6,029.19,” and added that total waived costs including lift equipment came to $6,469.19, meaning the county would “have no cost incurred in upgrading the lighting in our 2 barns.” Scheduling for the installations was estimated at about six weeks due to contractor workload.
The item was placed before the board as a contract/upgrade proposal. After a motion and second, the clerk called roll and recorded ‘Yes’ votes for Clark McClary, Larry Watson and Billy Cloud; the motion passed.
The commission did not discuss alternative bids, long-term energy-savings estimates, or a timetable for completion beyond the contractor's scheduling note. The item was handled on the consent/agenda track and approved without asking for additional funding from county coffers.
Next steps: the vendor will schedule the installations and county staff will coordinate access; no county appropriation was required for the equipment costs as presented.