Finance panel approves $36,016 contract for permanent sound system at Renaissance Park
Summary
The committee approved awarding a contract to New England Mobile Audio for a permanent outdoor sound system at Renaissance Park at a cost not to exceed $36,016, funded from Riverfront TIF bond and project contingency; Economic Development Director Liz Hannam said an installed system was more cost-effective than repeatedly renting equipment.
Get email alerts on the Park Infrastructure topic
No spam. Unsubscribe anytime.
Liz Hannam, the city's economic development director, told the Finance Committee the Riverfront project team added a permanent outdoor sound system to Renaissance Park after realizing rentals were not feasible for recurring events. Hannam said staff conducted an RFP with three quotes, value-engineered the proposal and secured a solution that was significantly less expensive than earlier estimates.
A purchasing communication proposed awarding a contract to New England Mobile Audio for the design and installation of a permanent outdoor sound system at Renaissance Park in an amount not to exceed $36,016, funded from the Riverfront TIF bond and project contingency. Hannam noted the vendor provided the system for free during a Riverwalk event as part of partnership support and manages another city site, Greeley Park.
After questions, the committee proceeded to a roll-call vote and approved the contract award. The project will be funded from the economic development fund (Riverfront TIF Bond) and the designated project contingency line.