Orlando council approves Cambria Suites downtown plan amid church concerns over construction impacts
Summary
The Orlando City Council approved Ordinance No. 20-26-23 to amend and restate the Cambria Suites plan development despite testimony from St. George Orthodox Church leaders and neighbors urging written monitoring and vibration safeguards; the developer and staff said the ordinance and MPB conditions require preconstruction structural inspections and monitoring agreements.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
The Orlando City Council voted July 13 to approve Ordinance No. 20-26-23, which amends and restates the Cambria Suites plan development for a downtown parcel near North Rosalind Avenue and North Magnolia Street. Commissioner Shan Rose moved approval and the council carried the motion by voice vote.
The decision followed an extended public-comment period focused on potential construction impacts to St. George Orthodox Church, a century-old building adjacent to the site. Father John Himadi, who identified himself as affiliated with St. George, told the council the church is a longtime provider of community services and urged the council to require enforceable protections that "run with the land" so future owners must address vibration and structural risks.
"I would like it — and I hope that you will put it in the ordinance ... whether it be this developer or someone that comes in in the future, they have to address these concerns," Father John said.
Another parishioner, Isaac Abdel Messiah, asked the council to require written monitoring and real-time sensors to detect vibrations, saying construction could harm the "fragile status" of the 100‑year‑old church. Resident and graduate student Natalie Xenofontos called for "strong structural reviews, monitoring, and safeguards" in the Lake Eola Heights Historic District before allowing deep excavation.
In response, the applicant's representative confirmed that the ordinance and staff conditions include preconstruction and ongoing measures intended to limit off‑site effects. The representative said the applicant must "provide at its sole expense a professional and certified structural inspection report for the immediately adjacent property" prior to issuance of building permits, meet with the church before inspecting, and that industry practice includes access agreements for installing vibration sensors and survey points.
Commissioner Rose emphasized that the municipal planning board (MPB) had placed geotechnical and vibration‑mitigation conditions in its recommendation and that those conditions appear in the staff report. Several commissioners said they had discussed foundation and monitoring concerns with both the developer and church representatives and expected staff and the applicant to follow the MPB conditions during permitting and construction oversight.
Supporters of the project and the applicant described it as a mixed hotel/residential development that will bring new housing and downtown activity. The developer and staff noted prior recommendations from the Appearance Review Board (ARB) and MPB and said the ordinance is conditioned on more than 30 items of approval that include construction methodology subject to city review.
The council approved the ordinance after the public comment period and applicant response. The mayor announced the motion carried by voice vote; no roll-call tally was recorded in the transcript.
What happens next: with the ordinance approved, staff will continue permitting review under the city's conditions of approval, which the applicant said will require structural inspections, benchmarking, and access agreements to allow monitoring during construction. The church and developer indicated they will continue their dialogue as the project moves forward.