Highland High School bids come in $24 million over estimate; district to consider redesigns
Summary
Construction bids for Highland High returned more than $24 million above the board’s estimate, prompting staff to propose design adjustments and value-engineering; West High phase 1 remains under budget, and crews will start above-ground work next week at West High.
Get email alerts on the Construction Bids topic
No spam. Unsubscribe anytime.
Isaac Estill, construction program staff, told the board that bids for Highland High were returned significantly higher than the estimate. The hard-construction bid came back at just over $280 million against a $255 million hard-construction budget, roughly $24 million above estimate.
Why it matters: Large bid overruns require either increased appropriation, value-engineering reductions, or other design changes that could affect project scope, schedule and the bond program's contingency planning.
What staff said: Estill said the district met that morning to discuss options and will return to the board with proposed design adjustments intended to close the gap. He described West High as a contrasting case where phase 1 bids came in about $4 million under projection and said panels and above-ground work will begin at West High the following week.
Board follow-up: Board members asked about parking and ADA connections for a Sugar House Park softball field tied to district work; Estill said existing parking will be connected with ADA sidewalks, and the team is negotiating temporary construction parking with local churches and park authorities.
Next steps: Staff will report back with design/rebid options for Highland and updates on project sequencing and cost implications for the bond program.