Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Quality topic

No spam. Unsubscribe anytime.

Board reviews lake tributary test results, considers annual baseline and targeted post‑project monitoring

Cedar Lake Stormwater Board · July 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Stormwater staff reported elevated suspended solids and pH at several tributaries feeding Cedar Lake and recommended establishing a baseline monitoring program (at least annually) and targeted testing after projects; cost reported at roughly $18,000 for 37 sample locations.

Stormwater staff presented results from recent water‑quality testing at six monitoring points feeding Cedar Lake and recommended maintaining a baseline program and doing targeted follow‑up testing after construction projects.

Schmiedt and Luke Sherry reviewed sampling locations and major findings: Lakeshore & Beverly; Sleepy Hollow by Lauerman; a wetland near Pinecrest Marina; the South Shore Tributary; South Shore Country Club; and Cedar Creek at the lake outflow. Several sites showed higher‑than‑expected suspended solids and dissolved solids; pH readings were also described as "off the charts" at one site.

Staff noted the sampling covered roughly 37 locations at a cost near $18,000 (about $600–$700 per site), and recommended at minimum annual testing to create a baseline and additional testing after projects (for example, after installing a sediment collection device or completing a sewer/storm improvement). Board members agreed an annual baseline made sense and asked staff to consider adding instruments or targeted post‑project tests.

The board discussed presentation options for public consumption; staff offered to format results for the town website so residents can view the main indicators. No formal funding decision was made; staff will include monitoring costs in future budget discussions.