Planning board grants 180-day extension to Sky Solar amid RG&E equipment and interconnection delays
Summary
The board approved a 180-day extension for the Sky Solar preliminary site plan to allow time for the applicant to secure new equipment and RG&E sign-off; board members asked for courtesy 90-day updates on progress.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Farmington Planning Board approved a 180-day extension for the Sky Solar preliminary site-plan review after the applicant requested more time to resolve equipment-supplier and RG&E interconnection matters.
Staff told the board the applicant initially asked for 120 days but has had to source alternative components because of federal regulations affecting available equipment. Board members discussed whether to grant 120, 180 days or a full-year extension and expressed concerns that RG&E response timelines are often longer than their estimates. The board settled on a 180-day extension and requested courtesy updates at roughly 90 days so staff and the board could monitor progress.
Several residents who had previously opposed the project asked that the board deny further delays, saying the applicant had already had multiple extensions. Board members discussed the trade-off between requiring a restart of the application (which could force the applicant to re-initiate interconnection discussions with RG&E) and the cost and time savings of allowing more time for the applicant to procure compliant components.
The board voted to approve the 180-day extension and asked staff to request an interim update from the applicant about RG&E engagement halfway through the extension period.