Benton County weighs $5,000 sidewalk repairs and larger courthouse drainage fixes
Summary
Supervisors reviewed two contractor quotes of about $5,000 each for sidewalk repairs and discussed a larger, unresolved courthouse water-intrusion issue that will likely require coordinated engineering plans and a rebid to ensure consistent contractor scope.
Get email alerts on the Facilities Maintenance topic
No spam. Unsubscribe anytime.
Benton County supervisors spent a substantial portion of the meeting on facility maintenance, weighing a near-term sidewalk repair contract and a longer-term courthouse drainage and foundation project.
Rick Wood reported the county had received two quotes “right around $5,000 a piece” to replace failing sidewalk squares and suggested pulling the work from capital funds. Supervisors debated whether to patch isolated areas or replace contiguous sections up to the property line; they also discussed preserving handicap-accessible approaches and the possibility of adding an adjacent fence project to the same scope.
Separately, staff described ongoing water intrusion around the courthouse, especially at the northwest corner and behind a transformer near the dumpster, where basement window wells and buried legacy features appear to be letting water into server and election equipment storage areas. Several supervisors warned the problem has worsened with heavy rains and said bidding a fix is difficult without a single set of engineering plans.
Members recommended engaging engineering expertise so all bidders would price the same work and suggested the assistant county engineer could help draw plans. The board agreed to inspect the site, gather clearer scope documents and, if necessary, rebid the project with a unified set of plans. No formal appropriation or contract award was completed at this meeting; the board directed staff to return with a written scope and budget recommendation.