City directs SEH to add spot repair to sewer-lining Phase 1; completion set for May 1, 2026
Summary
SEH Engineer Matt Schaible told the City of Richardton Commission that Phase 1 of the sanitary sewer lining project is on track for May 1, 2026; the commission directed SEH to add a spot repair to Phase 1 plans and authorized additional camera work for later phases.
Get email alerts on the Sanitary Sewer topic
No spam. Unsubscribe anytime.
SEH Engineer Matt Schaible updated the City of Richardton Commission on the sanitary sewer lining project, saying Phase 1 is scheduled for completion on May 1, 2026. The commission instructed SEH to add a spot repair to the current Phase 1 plans and to perform additional camera work to prepare for Phases 2 and 3.
The commission’s direction was procedural rather than a formal vote to amend contract documents; minutes record the instruction and the project timeline. The additional camera work is intended to identify conditions that will inform upcoming phases, according to Schaible’s presentation to the board.
Commissioners discussed project sequencing and the timetable for subsequent phases. No dollar amounts for the spot repair or additional camera work were provided in the minutes; the commission directed SEH to proceed with planning and necessary preliminary work.
The project timeline given in the meeting places Phase 1 completion on May 1, 2026. The commission did not record a motion to change project scope in the minutes; rather, the record reflects the commission’s direction to SEH staff to incorporate the spot repair in the Phase 1 plans and to perform extra camera inspections for future phases.