County highway updates: Co. Rd. 16 work progresses; other county roads reported complete

Richland County Board of Commissioners · October 15, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Highway staff reported Phase I of County Road 16 complete and Phase II underway with a change order to Flex Funding forthcoming; County Roads 8, 3, 26 and 2N were reported finished and staffing changes noted.

Jesse Sedler, representing the highway department, updated the board on ongoing county road work and staffing.

Sedler reported that Phase I of County Road 16 is complete; Phase II work is in progress toward Greatbend and Phase III will cover the portion west of the interstate. A change order for Co. Rd. 16 will be submitted to Flex Funding for reimbursement. Rumble strips, seeding and permanent sign work are expected to finish next week.

Sedler also told the board that County Roads 8, 3, 26 and 2N are complete. He noted that Mark Vetter’s last day with the department is that day.

The board took no formal action on highway projects at the meeting; Sedler’s updates were informational. Staff follow‑up on the Flex Funding reimbursement and routine project closeout steps were implied.