Courthouse renovation permit expected to enter state review; bidders to meet Aug. 26
Summary
Project presenters said they will submit the state permit package for the Petroleum County courthouse renovation within days and expect a 5–6 week review; a meeting with Representative Shane Klakken to review pricing bids is tentatively set for Aug. 26.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Presenters identified as Brad and Robie (participating by Zoom) updated the Petroleum County Commissioners on the courthouse renovation on July 22, saying they will follow up with the electrician about the generator and expect to submit the permit package to the state within days.
They told the board the state permit review typically takes about five to six weeks and estimated the review would be completed by early September. The presenters and the board tentatively scheduled a meeting for Aug. 26 with Representative Shane Klakken to review pricing bids.
No formal approvals or contract awards were recorded at the meeting.