Petroleum County commissioners report multiple grant applications for bridge work and courthouse HVAC
Summary
At the Nov. 4 mid‑month meeting, Petroleum County officials said the county has submitted grant applications — including an MCEP application for a Main Street bridge replacement and a Coal Grant application for courthouse HVAC — and that engineering and agency reviews are ongoing.
Get email alerts on the Grants And Infrastructure topic
No spam. Unsubscribe anytime.
Petroleum County commissioners on Nov. 4 heard updates that the county is pursuing outside funding for several infrastructure needs, including a submitted MCEP grant application for a Main Street bridge replacement and a Coal Grant application for courthouse HVAC improvements.
County Attorney Diane Cochran reported the Department of Natural Resources and Conservation is proofing legal descriptions of floodplain properties that would be used with a forthcoming resolution, and she told commissioners she has not yet received a response from the Boyer attorney about concerns tied to a contract for use of Boyer lots as a staging area.
Montana Department of Transportation notified the county that the Main Street bridge replacement "may qualify" for funding under a program referenced in the minutes as "58536." The county had already submitted an MCEP grant tied to the bridge expense, and the minutes say Stahley Engineering will continue to track program opportunities and advise the county. The minutes do not record further technical details or an application award timeline.
The county also submitted a Coal Grant application seeking funds for courthouse HVAC work. The minutes state the Coal Board will meet in mid‑December and announce decisions the same day.
Commissioners recorded that Katie Lund has agreed to help with bookkeeping for the Courthouse Rehab Project. Separately, a meeting to discuss floodplain compliance with river subdivision landowners was scheduled for Nov. 13, 2024.
No formal votes tied to grant awards or contract approvals were taken at the Nov. 4 meeting; the record lists grant submissions and agency notifications as items for staff and engineering consultants to continue monitoring.