Ruidoso Downs council approves $4,000 engineering amendment and accepts $3,497.58 contract reduction for park drainage project

Ruidoso Downs Village Council · November 14, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Ruidoso Downs Village Council on Nov. 13 approved a $4,000 amendment for additional engineering services on the All American Park Drainage Improvement Project and accepted a final change order reducing the contract by $3,497.58; councilors said the extra engineering cost will be covered by grant funds.

The Ruidoso Downs Village Council approved a $4,000 amendment to a task order for additional engineering on the All American Park Drainage Improvement Project and accepted a final change order reducing the project's contract price by $3,497.58 during its Nov. 13 meeting.

Joe Jarvis, a presenter to the council, told members the project had been delayed by a natural disaster and that the engineers "had to make 3 extra trips up here" which "increased their cost, by $4,000," and asked the council to approve charging the additional amount to the grant. The council voted to approve the amendment.

Councilors later reviewed Change Order No. 3 (final) for Renegade Construction LLC, which reflected final measured quantities and a reduction of $3,497.58 to the contract. The presenter described the adjustment as routine finalization of quantities; the council moved and voted to accept the change order.

Both actions were moved, seconded and carried during the meeting by voice/roll call; multiple councilors responded "Aye" during roll call votes. Meeting discussion also included a procedural exchange about whether a closed session on employee issues should wait until the town attorney could attend; councilors agreed to delay that item until legal counsel was present.

The meeting opened with the Pledge of Allegiance, roll call, and a brief update from a council member and public works representative that paving for an "east circle" location requires daytime temperatures of about 55°F and would take roughly three days when conditions permit. The council thanked staff and adjourned following new-business actions.

The meeting transcript records the motions and voice/roll-call affirmations but does not map every "Aye" to a named council member in a single consolidated tally in the record provided.