Commission continues review of proposed seawall repair and rebuild at 31 Water Street
Summary
The Ipswich Conservation Commission continued a hearing on a proposal to raze and rebuild a raised house at 31 Water Street, with in-kind seawall repair and new on-site stormwater controls; commissioners said the application lacks Riverfront Area evaluation, alternatives analysis for NDZ/NBZ waivers and requested a site visit and additional mitigation.
Get email alerts on the Shoreline And Floodplain Development topic
No spam. Unsubscribe anytime.
The Ipswich Conservation Commission on June 3 continued a public hearing on a Notice of Intent for 31 Water Street after commissioners raised regulatory gaps in the applicant's filing.
Scott Patrowicz, the project's engineer, and Courtney Simmons, representing the applicant, described plans to raze the existing dwelling and rebuild a raised two-story home within the same footprint, repair the existing seawall in-kind, place crushed stone under the new structure and use pervious pavers for the driveway. Patrowicz said current stormwater runoff on the property discharges to the Ipswich River and the proposal seeks to retain stormwater on site.
The property sits within FEMA’s AE flood zone (elevation 13) and includes areas inside the 25-foot No-Disturbance Zone (NDZ). Patrowicz described existing impervious surface of 1,036 square feet and proposed impervious area of 1,170 square feet. The applicants said the seawall work would maintain the existing footprint and height and that the proposed house would be supported on piles.
Chair Jennifer Hughes raised a series of substantive regulatory concerns. Hughes said the Riverfront Area analysis required under the Massachusetts Wetlands Protection Act and local bylaws had not been addressed, including whether the proposed patio and other features are allowable on riverfront. She said waivers (for NDZ/NBZ encroachments) require an alternatives analysis and that mitigation should meet the commission’s performance standards — the board noted mitigation was expected at roughly 1.5 times the disturbed area. Hughes also asked for documentation of Chapter 91 approval and additional detail on Coastal Bank performance standards.
Hughes proposed a site visit to review sensitive areas and constraints; the commission scheduled a site visit for June 9, 2026, at 5:30 p.m. Commissioner James Stone moved to continue the matter to the June 17, 2026 meeting; the motion was seconded and passed unanimously.
Next steps: the commission asked the applicant to provide a Riverfront Area evaluation, an alternatives analysis to justify requested NDZ/NBZ waivers, mitigation calculations, and a copy of any Chapter 91 approval before the continued hearing on June 17.