Kirtland reviews splash-pad plans and sewer implications before moving forward
Summary
Town Engineer Dan Flack presented splash-pad options and cost estimates, explaining a 10% contingency for nearly finished designs and 15% for pass-through arrangements. Councilors requested additional information and public bidding options and expressed concerns about maintenance and sewer impacts.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
Town Engineer Dan Flack told the council there were no major sewer-line breaks but raised technical and cost questions about a proposed splash pad. He said Exerplay provided the only firm quote; other vendors supplied estimates. Flack explained the difference in contingency—10% for projects where the design is nearly complete versus a 15% contingency for pass-through contracts—and said pass-through pricing affects costs and responsibilities.
Councilor Trujillo and Councilor Warner asked whether other vendors could be solicited; Flack said he bid the work through CES but could request additional options. The council discussed whether surplus funds could be used for ongoing maintenance of the splash pad; Flack said surplus funds could not be used for maintenance. Mayor Uhl suggested alternate approaches, such as using a tank system to irrigate nearby grass, and the council asked staff to provide more information on option two and on publicly bidding the project before making a decision.
No formal motion was taken to commit funds for construction; the council requested more detailed cost breakdowns, potential maintenance responsibilities, and clearer bidding options at a future meeting.