City awards $909,405 contract for Well No. 8 after waiving three‑bid rule

South Lyon City Council · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council voted to waive the three-bid minimum and awarded Sorensen Gross Company LLC a $909,405 contract to construct groundwater replacement Well No. 8; council also approved a budget amendment to raise the water-and-sewer capital line to reflect the increased cost.

Wastewater Superintendent Beeson presented the scope and funding for the groundwater replacement Well No. 8 project and said the work includes a well house, electrical and control systems, pump pedestal and about 400 feet of 8-inch HDPE pipe to connect to an existing 12-inch line in Makati Park. The project was budgeted at $800,000 for FY26–27, but the low bid from Sorensen Gross Company LLC was $909,405.

Beeson said two bids were received on BidNet and that HRC provided a letter of recommendation supporting the award to Sorensen Gross. Council member Hanson moved to waive the city’s three-bid minimum because only two bids were returned; the council voted in favor on a roll call. The council then approved awarding the contract to Sorensen Gross at $909,405 and later approved a water-and-sewer budget amendment to increase the GL account 592-556-972 from $1,569,000 to $1,678,405 to cover the higher cost.

Council members asked about procurement process timing and confirmed staff used an open-bid process through BidNet. Beeson estimated, subject to DTE power and other scheduling, construction could be completed by November or December if utilities and site preparation proceed; he noted additional contractors and coordination would be required.