Committee agrees to forward Straubel Springs outlet-works amendment increasing project cost to $9.3 million
Summary
The Water Policy Committee unanimously supported sending to council an amendment to the IGA with Denver Water that raises the Straubel Springs outlet-works project from $3.7 million to $9.3 million, increases Aurora's 5.73% share to $1.4 million and extends completion to June 2027.
Get email alerts on the Straubel Springs topic
No spam. Unsubscribe anytime.
Matthew presented an amendment to an existing intergovernmental agreement with Denver Water for the Straubel Springs Dam outlet-works refurbishment, saying the change is needed because total project costs are now projected to exceed the 10% threshold that triggers council approval. “The amendment is needed because the total project costs, is now projected to exceed the 10% threshold,” Matthew said.
He told the committee that after Denver’s standard procurement process produced no qualified bidders, Denver evaluated alternate delivery approaches and selected a sole‑source open‑book delivery to preserve schedule and allow ongoing cost validation. “This approach … allows costs to be validated throughout construction and supports collaborative risk management while maintaining the project schedule,” Matthew said.
Staff said the amendment increases the total project cost from $3,700,000 to $9,300,000 and extends the completion date to June 2027. Aurora Water’s 5.73% cost share increases from $582,000 to $1,400,000 (a change of $818,000). Committee members expressed support for forwarding the amendment to the full council: “No questions, and I support moving it forward,” Councilmember Lawson said, and Councilmember Andrews likewise voiced support.
The presenter requested the committee’s concurrence to forward the amendment for council consideration; members offered no substantive questions and the committee agreed to move the item forward. No formal roll‑call vote was recorded in the committee transcript; staff will transmit the amendment and supporting materials to the council packet for the next council meeting.
Next steps: staff will place the amendment on the council agenda and provide detailed procurement and cost documentation to the council per the IGA and city procurement requirements.