Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Budget topic
No spam. Unsubscribe anytime.
Orange Select Board reviews 2025 budget and notes town-shed project delay
Summary
The Select Board reviewed municipal spending through Aug. 31, 2025 (about 70% of budget spent) and heard that the town-shed project and land donation are delayed; board staff said remaining funds must be spent in 2025 or properly encumbered, and auditors will meet this week to complete required reports.
Get email alerts on the Budget topic
No spam. Unsubscribe anytime.
The Orange Select Board reviewed the town's 2025 finances and was told the town-shed project is running behind schedule, requiring prompt accounting steps.
At the meeting Sept. 2, Catherine Souza, the town clerk/secretary, reported municipal expenses through Aug. 31 totaled $303,055.73 against an approved 2025 budget of $431,174.00, roughly 70% spent to date. Souza said the Road Agent and the Select Board will enter remaining contracts related to the shed and the associated land donation to ensure funds are used appropriately before year-end.
Souza also said that "according to the law regarding the town vote" any remaining money tied to that vote must be spent in 2025 or properly encumbered. The meeting record does not specify the statute or ordinance that establishes the deadline. The Select Board intends to address the accounting and contracting steps to comply with that requirement.
Auditor Tim Greene of Roberts & Greene is scheduled to meet with Souza and Trish at the town office on Sept. 3 to complete the MS-535 financial report. Souza also said the MS-01 town inventory valuation report had been granted an extension because the revaluation data were required to complete it.
The Select Board confirmed it will continue tracking the shed project and related spending; the next Select Board meeting is set for Sept. 16, 2025, at 6 p.m.
