Technology and maintenance directors told the board on June 10 that computer imaging and a firmware update are underway, three failed elementary switches will be replaced, the high school chiller is installed and electricians will wire it, roofing is nearly complete, pool liners were repaired and crews are ordering longer drill bits and a larger rig to finish football-field core drilling.
Get email alerts on the Facilities Operations topic
No spam. Unsubscribe anytime.
Technology and maintenance directors updated the board on a series of ongoing facilities and operations projects at the June 10 meeting.
Technology Director Beau Gregory said computer imaging for district machines is proceeding, with most middle school computers completed. Gregory reported an elementary firmware update and that three stackable switches in an elementary hallway are not functioning; the district has ordered three replacement switches to be reconfigured and installed.
Maintenance Director Adam Ertman reported that the high school chiller has been set in place and bolted; electricians are scheduled to wire the unit and Long's Technology will install the controller, with the district hoping to have the high school air conditioning operating by the middle of next week. Ertman said roofing work is wrapping up and that pool liners required repairs; crews were refilling, beginning to heat and add chemicals with an expected reopening by Monday. On a football‑field drainage project, crews could not core through a clay layer; Ertman said they ordered longer drill‑bit extensions and a larger machine to finish drilling so they can fill cores with sand to improve filtration.
Ertman also described the district's bidding process for projects.