Vero Beach updates on water reclamation, septic-to-sewer, Humiston boardwalk and Three Corners progress

Vero Beach City Council · February 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported the Water Reclamation Facility remains on schedule for construction in December with online operations by summer 2028; septic-to-sewer bids and grants are progressing on the mainland; FDEP permitting for the Conn Beach/Humiston Park boardwalk will be submitted and construction is slated to start Nov. 1; developer funds and a Letter of Intent are expected for the Three Corners project.

Several large infrastructure projects featured in the Vero Beach Feb. 3 workshop, with staff giving progress reports and near-term milestones.

Water & Sewer Director Rob Bolton said the Water Reclamation Facility remains on schedule: construction is planned to start in December and the facility should be online by summer 2028. Bolton showed before-and-after filtration visuals for stormwater and said contingency funds have not been tapped so far.

On septic-to-sewer work, Bolton said bids for Ocean Ridge have been issued and mainland areas secured two grants to pay for mains. He noted some barrier-island properties (outside the B-map) are not eligible for grants; staff may require property owners to connect within one year of sale, and Bolton will return with proposed compliance steps.

Public Works Director Matt Mitts said permitting with the Florida Department of Environmental Protection for the Conn Beach/Humiston Park boardwalk will be submitted the week of the workshop and that construction is planned to begin Nov. 1 to avoid sea turtle nesting season; staff intend to include an ADA ramp and a second shelter in the design. City Manager Monte Falls said fundraising is ongoing to close an estimated $2 million gap, and he has engaged the congressional delegation for appropriations.

Falls reported that for the Three Corners site the city expects a $50,000 deposit from the developer and a signed Letter of Intent to begin negotiations after a meeting with the city's financial consultant.

Staff offered no final decisions at the workshop; council asked for progress updates as permits, grant awards and contracts advance.