Harbor Market site plan conditionally approved pending engineering sign-off on drainage
Summary
Commissioners signaled support for the Harbor Market 300 Lake Street plan but required Beckett Raider and the city engineer to review revised drainage details submitted the prior day before final approval; staff and the applicant agreed to a contingent approval process to avoid delaying seasonal paving work.
Get email alerts on the Site Plan 300 Lake St topic
No spam. Unsubscribe anytime.
The Harbor Springs Planning Commission on July 16 offered conditional support for the Harbor Market site plan at 300 Lake Street, agreeing to a staff‑led contingent approval if the city's consulting engineer and zoning administrator endorse the revised drainage materials submitted by the applicant.
Applicant engineer Aaron Nordman of Performance Engineers told the commission the revised plan replaces deteriorated pavement, adds approximately seven parking spaces, creates two small retention areas and includes an overflow pipe to the city system intended to reduce standing water on Traverse Street. Nordman said the changes would move traffic out of the recycling area and improve an existing public nuisance.
Staff and Beckett Raider's initial review flagged deficient drainage detail and asked for updated grading and drainage information; the applicant delivered a revised plan the day before the meeting and the commission's consultant had not completed a full review. Commissioners debated consistency with earlier decisions (some members noted the commission recently denied another project because of drainage problems) and discussed a limited, contingent approval that would allow the applicant to keep a contractor schedule if consultants confirm the revised plan addresses prior deficiencies.
The commission voted to authorize Beckett Raider and the zoning administrator to review the revised submission and to permit staff to finalize approval if those reviewers deem it compliant with the ordinance and engineering standards. If reviewers find the plan insufficient, the item will return to the full commission.
The applicant said schedule pressures (contractor availability) motivated the request for quick action; staff said a special meeting could be posted on short notice if consultant review uncovered material issues.
Next steps: Beckett Raider and staff will review the revised drainage plan and notify the commission whether staff has authority to finalize approval or whether the commission must reconvene for further action.