Grafton council approves $152,300 interior rehab for water tower after inspection

City of Grafton City Council · June 16, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a June 16 special meeting, the Grafton City Council voted unanimously to approve Change Order #1 for the water tower project, choosing a full interior rehabilitation option for $152,300 to address cracking coating found during an inspection; the work will be paid from Prairie Dog Funds.

Grafton City Council approved Change Order #1 for the city’s water tower project on June 16, selecting a full interior rehabilitation that will cost $152,300 and be financed from Prairie Dog Funds.

Water Superintendent Tom Dusek reported that Viking Painting, LLC inspected the water tower’s interior and found the coating cracking in several spots, with additional repairs needed mainly on the bottom and side walls. Viking provided three repair estimates: a full interior sandblast of roof, walls and floor for $152,300 (Option 1); roughening and taking belly and risers to metal for $142,700 (Option 2); and an interior wet brush blast to remove surface shine for $95,800 (Option 3). Dusek recommended Option 1, saying it would be “in our best interest” to pay the approximately $9,600 premium to take the finish down to bare metal and complete a total rehab.

Councilmember Brad Burianek moved to approve Viking Painting, LLC Change Order #1 selecting Option 1 for $152,300, and Councilmember Greg Young seconded. On a roll-call vote, Councilmembers Brad Burianek, Kylen Kostrzewski, Donavon McMillian, Loree Osowski, Phil Ray, Darrin Wollitz and Greg Young voted in favor; none opposed. One council position remained vacant. Mayor Chris West declared the motion carried.

The special meeting began at 5:30 p.m. in the City Hall Council Chambers and was adjourned at 5:35 p.m. after the council’s action. The minutes list Nick Ziegelmann, Ed Sevigny, Tom Dusek and Jeff Daley as other attendees; the minutes are signed by Mayor Chris West and Wanda Ensrude, City Auditor.

The approved full interior rehab will remove the existing finish down to metal and address the cracking noted in the inspection. The council’s minutes do not specify a project start date, timeline for completion, or contractor schedule; those details were not included in the record.